Shanghai Weiye Optic Fiber Communication Equipment Co., Ltd. provides equipment for producing rollable formats used in optical-fiber manufacturing. Buyers can evaluate the capacity of this setup against their intended product range because it is designed for 12- and 16-fiber ribbons. Its split-type construction may also influence factory space and installation requirements.
Fiber Coloring Machine Fiber Draw Tower Fiber Coloring Machine
The stated construction speed for this particular production line is 600 m/min. Fiber pay-off, gathering and guiding, intermittent resin dispensing, UV-LED curing, visual monitoring, capstan pulling, and take-up are combined in the process. When assessing suitability, the complete process matters rather than speed alone.
Factory utilities, reel requirements, available floor space, and installation conditions should be assessed before purchase. Ask the supplier for its documentation package and confirm the system’s suitability for your cable design and operating requirements. Early planning for these details can minimize setup delays and make startup smoother.
Key Takeaways
- Designed for rollable 12- and 16-fiber formats.
- Listed speed: 600 m/min for this equipment.
- Uses a split-type construction.
- Curing, monitoring, pulling, and take-up stages are included.
- Before purchasing, verify utilities, reels, installation requirements, and supplier documentation.
Intermittent Bonded Ribbon Production Line
Explore The Intermittent Bonded Ribbon Production Line
Three mold groups help shape rollable IBR formats by positioning fibers for small adhesive dots. Operators can adjust the mold position from 0 to 15 mm to support consistent spacing and shape.
Make Rollable Fiber Ribbons Using Precision Bonding
A 16-spool pay-off supplies fiber to the machine, while guide rollers with U-shaped grooves keep individual strands organized. Steady contact during processing is supported by the rollers’ hard-anodized surfaces. For 12F and 16F layouts, the adjustable valve setup uses 5+5+1 valves for 12 fibers or 5+5+5 for 16. Confirm the required tension control settings with the supplier for your cable design.
Support 12- And 16-Fiber Configurations At Speeds Up To 600 m/min
The stated construction speed reaches 600 m/min. Pay-off reel options hold 25.2 km or 50.4 km of fiber according to the listed reel dimensions: Φ236 mm × Φ25.4 mm × 108 mm and Φ267 mm × Φ25.4 mm × 180 mm. The system also provides T-type or fiber-optic take-up reels. Compare reel capacity with your operational requirements and expected changeover time.
Review The Production Line’s Key Equipment And Controls
Tension, resin placement, and UV exposure must work together to deliver reliable output. Operators can use the system to align settings with the needs of their cable design and fiber ribbon.
Manage Fiber Tension, Resin Dispensing, And UV-LED Curing Together
Every pay-off unit uses electro-pneumatic adjustment. Through the interface, operators set adhesive-dot spacing and counts while dispensers work individually or in linked groups.
Before UV-LED post-curing, three pre-curing ovens work with the mold groups. Ask the supplier to check resin compatibility and the relevant operating conditions.
Lamp current, oven temperature, alarms, and preset lengths are displayed or managed through the Siemens PLC and touchscreen. Before purchase, review cabinet requirements and power supply needs.
| Process Stage | Specification | Buyer verification |
| Fiber tension | Pay-off tension: 0.4 to 2 N with ±0.02 N; capstan tension: 50 to 500 g with ±5 g accuracy | Align settings with cable requirements |
| Resin dispensing | Independent or linked units; set adhesive-dot spacing and count | Review interface settings |
| UV-LED curing | Three 800 W pre-curing ovens; one 6 kW post-curing oven; 395 nm ± 3 nm; at least 85% cure under stable, high-speed conditions | Confirm resin compatibility |
| Process monitoring | Siemens S7-1200 or S7-1500 PLC; 10.4-inch touchscreen; real-time lamp current and oven temperature, alarms, preset lengths | Verify cabinet and power supply requirements |
Prepare Line Configuration, Installation, And Operating Conditions
Before the machine is delivered, prepare a dedicated operating area. An enclosed, clean, dry, draft-free space is needed for the optical fibre system. Maintain temperatures between 15°C and 25°C and humidity at or below 85%. Maintaining these conditions supports equipment protection and operating precision.
With your facilities team, assess site utilities, available electrical capacity, cabinet space, and cable design. The system needs nitrogen supplied at 7 bar and 99.99% purity, together with compressed air at 6 bar. A three-phase, five-wire electrical supply rated 380 V ±10% is specified.
- Reserve room for the cabinet, components, resin, and access to service parts. Verify temperature settings and tension control before startup.
- Account for the specified reel size of Φ410 mm × Φ50.8 mm × 391 mm. Reels of up to 30 kg can be handled by the take-up unit.
- Account for the main power feed-in cable when planning the site. The equipment package excludes connection cables and cable trays.
Before ordering, confirm the supply scope, reel types, and installation requirements. This assessment can reduce setup time and help prevent later delays. Request supplier confirmation of appropriate settings for your fiber and cable design, including lamp accuracy and operating conditions. Clear planning supports a smoother startup for the production system.
Request Pricing For A Ribbon Production Solution Tailored To Your Needs
Manufacturers seeking rollable 12- or 16-fiber formats can evaluate this line at its stated speed of 600 m/min. Share details of your fiber layout, output targets, cable requirements, reel preferences, and factory conditions to obtain a quotation.
Check the proposed system for its 16-spool pay-off, UV-LED curing setup, take-up capacity, and available options. Examine the supplied components, dispensing-head options, unit functions, and cable design prior to ordering.
The documentation list includes operating and maintenance manuals, a general layout drawing, electrical schematics, and a wear-parts list. These documents can help understand setup time and ongoing service needs.
Contact Shanghai Weiye Optic Fiber Communication Equipment Co., Ltd. to obtain pricing and configuration details that suit your output plan and site utilities. Verify the supply scope and replacement parts before purchase.